/Local News/ High Barnet//5 min read

Archway Heights residents face sixth year of scaffolding

Intruders and anti-social behaviour plague homes as cladding repairs remain stalled.

Trust 60Craft 70Hype 45How this was reported ▾
Trust60/100

Central claims attributed to named bodies and residents, with specific dates and figures provided.

How well corroborated and evidenced the reporting is. Higher is better.

Craft70/100

Reporting clearly separates fact from comment, quotes affected parties, and explains what happens next.

Context, balance and separation of fact from comment. Higher is better.

Hype45/100

Headline uses 'nightmare' but the article details specific resident experiences and official delays.

How far presentation runs ahead of substance. Lower is better.

1 source assessed · methodology

By Barnet Press News DeskAI-assisted, editor-supervised • Barnet Press
Published: Barnet Edition • Verified local news
Share Story:
Archway Heights residents face sixth year of scaffolding

Residents at Archway Heights have reported intruders accessing scaffolding around their homes for the past six years. The scaffolding was put in place in 2020 as a safety measure after a section of external cladding detached from the building. People for Places, the housing association, stated that it is awaiting approval from the Building Safety Regulator (BSR) to begin the necessary repairs.

The Building Safety Regulator confirmed that an application submitted in 2024 was invalidated, and further information is required to ensure compliance with building regulations. This delay has left residents feeling uncertain about the safety of their homes and the timeline for resolution.

Read Next in Barnet Press4 min read
Residents bid to buy back derelict High Barnet youth club

Residents bid to buy back derelict High Barnet youth club

Quinta Village Green Residents’ Association submits offer for former youth club, valued at £300,000 by Barnet Council.

Concerns over safety and security

Natasha Dyett, who has lived in the nine-storey block for two years, described the situation as a "nightmare". She reported seeing individuals on the scaffolding outside her window during the summer, leading her to keep her home sealed. Dyett recounted an incident in July where she saw a person standing outside her window, prompting her to alert her landlord. She noted that CCTV footage was reportedly wiped before it could be reviewed. Residents frequently report people on the scaffolding, with concerns that they can access the roof. The scaffolding's presence has also led to increased energy costs for some residents who keep lights on during the day due to reduced natural light.

Ciara Squires, a 34-year-old nurse, also reported seeing individuals on the scaffolding and found returning home frightening due to loiterers. CCTV footage has previously captured incidents involving multiple individuals. Jameel Choudhury, who resides at Archway Heights with his family, highlighted that the scaffolding has attracted rough sleepers who have occupied the building's cycle and storage areas. He described seeing people accessing the scaffolding, breaking into the cycle store, and engaging in anti-social behaviour, including drug dealing. Choudhury noted that items like duvets, chairs, and a microwave were found in the storage area, where individuals were cooking and charging devices, with children in nearby bedrooms able to hear the activity.

Related Borough Coverage3 min read
Barnet magistrate backs national drive for new recruits

Barnet magistrate backs national drive for new recruits

Gwilwyn Wright JP highlights everyday skills needed for the role in Ministry of Justice campaign.

Residents have also expressed concerns about the cladding itself, questioning its safety and flammability. Choudhury stated that residents are seeking clear information about the situation and confirmation that the building is safe.

Delayed repairs and regulatory hurdles

A spokesperson for People for Places confirmed that additional security measures have been implemented at the block. Planning approval was obtained in 2023, and a contractor was appointed. However, changes introduced by the Building Safety Act for higher-risk buildings necessitated further approvals. Origin Housing, which merged with People for Places in April 2024, submitted an application in 2024 that required resubmission in January 2025. The full integration of the organisations was completed in April 2026.

People for Places stated that they are awaiting a decision from the BSR before the 12-month repair programme can commence. The spokesperson acknowledged the complexity and duration of the issues, expressing a desire to progress the works as swiftly as possible. The BSR, established to reform building safety laws, is working with the applicant on the proposed remediation works for the façade identified in 2020. The regulator noted that the case, initially submitted in April 2024, was invalidated, and the subsequent application in January 2025 has required multiple requests for further information.

Acorn Community Union is supporting residents who feel they have been left in limbo. Dan Newcombe, the union's media spokesperson, stated that residents have received shifting timelines for decisions over the past six years, with conflicting information from the housing association and the Building Safety Regulator leaving them without a clear end in sight. People for Places has indicated that a detailed work programme will be provided to residents once approval is granted.

6YearsScaffolding has surrounded Archway Heights homes.
12MonthsExpected duration of repair works once approved.

Questions this report answers

+Why has the scaffolding been up for so long?

The scaffolding was erected in 2020 due to a piece of cladding falling off. Repairs are now delayed because the Building Safety Regulator invalidated an application in 2024 and requires more information to approve the work.

+What problems are residents facing because of the scaffolding?

Residents have reported intruders accessing the scaffolding for six years, leading to security concerns and anti-social behaviour. Some individuals have used the scaffolding and storage areas for sleeping and other activities, causing distress to residents.

+When will the repairs to Archway Heights be completed?

The housing association, People for Places, is awaiting approval from the Building Safety Regulator before commencing repairs. Once approved, the work is expected to take 12 months to complete.

Barnet Press News Desk

This article was written at the Barnet Press news desk from the reporting of the outlets listed below it. Drafting is done by a language model under human editorial supervision — there is no reporter behind this byline, and we would rather say so than invent one.

How stories are produced and scoredWho runs Barnet PressCorrections

Live in the borough

Barnet conditions

Loading live conditions…

More Coverage in Local News

Residents bid to buy back derelict High Barnet youth club
High Barnet

Residents bid to buy back derelict High Barnet youth club

4 min read
Barnet magistrate backs national drive for new recruits
High Barnet

Barnet magistrate backs national drive for new recruits

3 min read
Community orchard planned for Barnet Playing Fields
High Barnet

Community orchard planned for Barnet Playing Fields

3 min read
Barnet Guild of Artists to relocate after 60 years at Whalebones
High Barnet

Barnet Guild of Artists to relocate after 60 years at Whalebones